Electricity

Electricity

Lanes Flat (alterations to Mana 33kV circuit)

Client: Northpower (Wellington Electricity)

Location: SH58 Pauatahanui

We recently completed project works for Northpower / Wellington Electricity to the Mana 33kV circuit as part of the roundabout reconfiguration (Transmission Gully), civils works included trench construction, directional drilling, cable hauling, pole & earth installation and reinstated, has been a great project, have attached some extra pictures to the photo gallery hope they would tell the rest of the story

Duration: January – February 2016 (6 Weeks)

Water

Water

Clutha Ave Water Lateral Replacement

Client: Ives Plumbing (Wellington Water)

Location: Clutha Ave (Khandallah)

Description: Relocation of water service connections, the vermeer D9x13 was ideal tackling difficult locations with minimal disturbance

Duration: March 2016 (3 days)

Gas

Gas

Central Wellington (Project Neon)

Client: Downer (Powerco)

Location: The Terrace (Wellington)

Description: Ensure the gas network pipe is suitable for the upgraded 210kPa operating pressure. This project was to test and commission 60 - 80 existing services along the Terrace and immediate streets above The Terrance, including Bowen Street, Boulcott Street & Plimmer Steps.

Duration: Dec 2014 - July 2015 (6 months)

Civil Works

Civil Works

Karori Road Retaining Wall Renewal

Client: RCC (Wellington City Council)

Location: 123-133 Karori Road (Wellington)

Description: Install 32mm & 63mm continuous HDPE ducting within property boundaries for relocation of existing overhead services (electricity & telecommunications)

Duration: September 2015 (2 weeks)

Water

Water

Southern Water Mains Contract (W1235)

Client: Wellington Pipelines (Wellington Water)

Locations: Dundas Street (Seatoun) & Derwent Street (Island Bay)

Recently we completed installtation of 1x63mm water main installation along Dundas Street (Seatoun) & Derwent Street (Island Bay), works completed for Wellington Pipelines/Wellington Water

Duration: February - March 2016 (4 weeks)

Telecommunications

Telecommunications

Ultra Fast Broadband (UFB)

Client: Downer (Chorus)

Location: Wellington Region

Description: We have been engaged with directional drilling capabilities and have delivered over 30 cabinets within the Wellington Region

Duration: 2011 - 2016 (5 Years)

Electricity

Electricity

Dowse Art Museum (Skate Rink Power Supply)

Client: Northpower (Wellington Electricity) including Petone Electrical

Location: Myrtle Street & Dowse Art Museum (Lower Hutt)

Description: Install 1x110mm continuous HDPE pipe (directional drill) & haul 1x185mm2 4c XLPE cable across Myrtle Street from existing Wellington Electricity substation to the Dowse Art Museum and including an extension within the Dowse Art Museum to new electrical cabinet

Duration: August 2015 (2 weeks)

Water

Water

Wellington City Council (contract W1222)

Ngiao Water Main Renewal

Client: ERN Ramsbottom (Wellington Water Ltd)

Location: Mysore Street (Ngiao)

Descripton: Install 1x63mm continuous HDPE pipe (directional drill) in Mysore Street Ngaio (approximate 200m distance). We utilised the vermeer D9x13 directional drill for its ability to access the narrow walkway above Mysore Street

Duration: October 2015 (3 days)

 
© 2019 Aidan Kelly | Site map | Search | Terms & Conditions